Question: In optimizing the plan, Fazila is considering using deadlines for tasks. All the following are true about setting deadlines for tasks except: Question 17 options:
In optimizing the plan, Fazila is considering using deadlines for tasks. All the following are true about setting deadlines for tasks except: Question 17 options: If the task's finish date moves past its deadline date, Project creates an indicator. Setting semi-flexible constraints are better choices that setting task deadlines. The deadlines for tasks constrain the scheduling of the task. Project displays a deadline symbol on the chart portion of a Gantt chart view