Question: In PERT analysis, an activity has an optimistic time (to complete) of 4, and a pessimistic time of 8. Its mean (average) activity time is
In PERT analysis, an activity has an optimistic time (to complete) of 4, and a pessimistic time of 8. Its mean (average) activity time is 5. What is the most likely duration for this activity?
Group of answer choices
4.5
5
6
6.5