Question: Question 2 3 . 0 3 pts Activity slack refers to the difference between: Latest and earliest start times Finish and start times Observed and
Question
pts
Activity slack refers to the difference between:
Latest and earliest start times
Finish and start times
Observed and predicted times
Optimistic and pessimistic times