Question: In project schedule management, which process primarily involve identifying and documenting the relationships between project activities? a . defining activities b . planning schedule management

In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?
a.
defining activities
b.
planning schedule management
c.
sequencing activities
d.
estimating activity durations