In the case of NCC Cranberry, what are the solution options for the following assumptions? Assuming 8.5
Fantastic news! We've Found the answer you've been seeking!
Question:
In the case of NCC Cranberry, what are the solution options for the following assumptions?
Assuming 8.5 employees work 5.6 hours of overtime per day after 11 pm (end of second shift), the overtime hours saved over 105 days would be 5.6 hours.
The calculations show that the cost of overtime is less than the cost of a new dryer, thus not justifying the purchase of a dryer.
Overtime = 8.5 man * $8 * 1.5 * 5.6 * 102 days = $58262.4
Caselink
Related Book For
Introduction to Management Science A Modeling and Cases Studies Approach with Spreadsheets
ISBN: 978-0078024061
5th edition
Authors: Frederick S. Hillier, Mark S. Hillier
Posted Date: