Question: In the drum - buffer - rope conceptualization used in the theory of constraints, the buffer refers to Multiple Choice work - in - process

In the drum-buffer-rope conceptualization used in the theory of constraints, the "buffer" refers to
Multiple Choice
work-in-process inventory before the bottleneck.
the bottleneck operation.
job sequencing.
the master schedule.