Question: In the following image, what do the red bars indicate? Resource: John Smith Hours 80 40 0 Week of 1-lanlan 15-lan 22-Jan 2916-Feb 11-Feb 20

 In the following image, what do the red bars indicate? Resource:

In the following image, what do the red bars indicate? Resource: John Smith Hours 80 40 0 Week of 1-lanlan 15-lan 22-Jan 2916-Feb 11-Feb 20 Feb 27-Jan Select one: O a. The resource will be sharing his workload with another resource during that time. b. The resource will need to work overtime to accomplish his work. OG The project manager has made an error in the initial project plan. d. The project manager needs to 'level' the resource's work hours or re-assign some