Question: In the following network, manually level your resources so that you may not use more than 7 laborers per day at any time. Activity Predecessor

In the following network, manually level your resources so that you may not use more than 7 laborers per day at any time.

Activity Predecessor Duration (Days) Labors
A - 2 4
B - 3 2
C A 1 6
D A, B 3 3
E C, D 2 1

The company can provide only 7 labors per day. Thus

1. Draw the network.

2. Allocate resources.

3. Level the resources.