Question: In the following network, manually level your resources so that you may not use more than 7 laborers per day at any time. Activity Predecessor
In the following network, manually level your resources so that you may not use more than 7 laborers per day at any time.
| Activity | Predecessor | Duration (Days) | Labors |
| A | - | 2 | 4 |
| B | - | 3 | 2 |
| C | A | 1 | 6 |
| D | A, B | 3 | 3 |
| E | C, D | 2 | 1 |
The company can provide only 7 labors per day. Thus
1. Draw the network.
2. Allocate resources.
3. Level the resources.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts