Question: Option #1: Resource Loading with Nine (9) Laborers In the following network, manually level your resources so that you may not use more than nine
Option #1: Resource Loading with Nine (9) Laborers
In the following network, manually level your resources so that you may not use more than nine laborers per day at any time:
| Activity | Duration (Days) | IPA | Laborers |
| A | 2 | 3 | |
| B | 4 | A | 2 |
| C | 6 | A | 4 |
| D | 9 | A | 3 |
| E | 5 | B | 4 |
| F | 7 | B, C | 2 |
| G | 3 | D, E, F | 4 |
Deliverables:
- In an Excel spreadsheet, demonstrate the activities before they are leveled and after they are leveled. Draw a network diagram representing the activities before leveling the resources, and one after leveling the resources. Submit the network diagrams in .pdf format with your Excel spreadsheet.
Please focus the answer on the bolded portion. Hoping to see the network diagram both before and after leveling. Then if willing to answer two parts what it should look like before and after leveled in excel? A snippet from excel would be great!