Question: In the following network, manually level your resources so that you may not use more than nine laborers per day at any time. Activity Duration
In the following network, manually level your resources so that you may not use more than nine laborers per day at any time.
Activity Duration (Days) IPA Laborers A 2 – 3 B 4 A 2 C 6 A 4 D 9 A 3 E 5 B 4 F 7 B, C 2 G 3 D, E, F 4