Question: I've checked my question. In the following table, task durations are given in weeks. The estimates were made at the 9 5 percent level (

I've checked my question.
In the following table, task durations are given in
weeks. The estimates were made at the
9
5
percent
level
(
see Section
5
.
2
,
Calculating Probabilistic
Activity Times subsection
)
.
Activity Predec. Opt. Normal Pess.
a
2
4
6
b
3
5
9
c a
4
5
7
d a
4
6
1
0
e b
,
c
4
5
7
f d
3
4
8
g e
3
5
8
(
a
)
Find the expected time and variance for each task.
(
b
)
Draw the network
(
either AOA or AON
)
and
find the path with the longest expected time.
What is the expected time to complete this path?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!