Question: In the following table the activities with their precedence sequence and expected time (weeks) are listed for a project: Activity Immediate Predecessors Time (weeks) A
In the following table the activities with their precedence sequence and expected time (weeks) are listed for a project:
| Activity | Immediate Predecessors | Time (weeks) |
| A | - | 4 |
| B | - | 3 |
| C | A | 2 |
| D | A | 1 |
| E | B | 4 |
| F | B | 6 |
| G | C,E | 7 |
| H | E,F | 3 |
- Draw an AON Diagram:
2. Fill in all blank boxes of the following chart:
| Activity | Time (Weeks) | ES | EF | LS | LF | Slack | Critical Path? (yes or no) |
| A | |||||||
| B | |||||||
| C | |||||||
| D | |||||||
| E | |||||||
| F | |||||||
| G | |||||||
| H |
3. Critical path is _______________.
4. Total project completion time is ________________ weeks.
If somebody can answer this for me I would really appreciate it. Thank you in advance!
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock