Question: In the following table the activities with their precedence sequence and expected time (weeks) are listed for a project: Activity Immediate Predecessors Time (weeks) A

In the following table the activities with their precedence sequence and expected time (weeks) are listed for a project:

Activity Immediate Predecessors Time (weeks)
A - 4
B - 3
C A 2
D A 1
E B 4
F B 6
G C,E 7
H E,F 3
  1. Draw an AON Diagram:

2. Fill in all blank boxes of the following chart:

Activity Time (Weeks) ES EF LS LF Slack Critical Path? (yes or no)
A
B
C
D
E
F
G
H

3. Critical path is _______________.

4. Total project completion time is ________________ weeks.

If somebody can answer this for me I would really appreciate it. Thank you in advance!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!