Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) B A D

In the following table the activities with their
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) B A D B E B F EF D GH O O O I Time (days) 6 2 4 5 5 5 2 3 5 G Oh Noh 1 a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F-G-1