Question: In the hand simulation of the simple processing system, suppose the drill press is taken down for burn-in maintenance at time 4 minutes, and it
In the hand simulation of the simple processing system, suppose the drill press
is taken down for burn-in maintenance at time 4 minutes, and it takes 4 minutes to do
this work and bring it back up; it then stays up for the rest of the 20-minute simulation
length. If theres a part in service when the drill press goes down, it just sits there,
its processing suspended until the drill press comes back up, when its resumed and
needs just its remaining processing time (its processing does not have to start over from
scratch). During the down time, the arrival process of new parts continues without re
gard to down time. Regard the drill press as being busy when its down, and defi ne the
time in system of a part to include the time it sits in the drill press but not being worked
on if its unlucky enough to be in service when the drill press is taken down. Using the
same input data as in Table 2-1 , carry out this simulation by hand and note any differ
ences in the output performance measures from the original model. (See Exercise 6-18
for the question of whether this model change induces statistically signifi cant changes
in the output performance measures.)