Question: In the Module Overview, we stated that an aggregate plan will include the quantity and timing of production for the intermediate future ( typically 3

In the Module Overview, we stated that an "aggregate plan will include the quantity and timing of production for the intermediate future (typically 3-18 months ahead). Some factors such as demand, pay rate, and the ability to use overtime or subcontract some of the production must be taken into consideration to keep the total cost of production as low as possible.
You have been asked to build the aggregate planning schedule for your factory for the next six months and to determine the best option.
This chart provides the variables and cost for each variable.
Variables Cost
Inventory carrying cost $7 per unit per month
Subcontracting cost $25 per unit
Average pay rate $12 per hour (8 hours per day)
Overtime pay rate $18 per hour (above 8 hours per day)
Labor-hours needed to produce one unit 1.5 hours per unit
Units per day produced 50
Beginning inventory 0
Planned ending inventory 0
Lost sales per unit $30
This chart provides the demand for the product and the number of production days per month.
Months Demand Production Days
January 120022
February 80018
March 60021
April 150021
May 130022
June 120020

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!