Question: In the network diagram below, there are five activities with finish - to - start dependencies. The numbers display the duration of each activity as
In the network diagram below, there are five activities with finishtostart dependencies. The numbers display the duration of each activity as days.
Which one of the following statements is WRONG about the activities or the project?
A
The overall project duration is days.
B
The late finish day is days for activities B and C
C
The slacks are zero for activities B C and D
D
The critical path includes activities A D and E