Question: In the probabilistic approach to project network analysis, the time estimate annotated t m for any activity is the: mean time median time

In the probabilistic approach to project network analysis, the time estimate annotated "t m" for any activity is the:
mean time
median time
most likely time
mode time
 In the probabilistic approach to project network analysis, the time estimate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!