Question: In the probabilistic approach to project network analysis, the time estimate annotated t m for any activity is the Multiple Choice 0 8 : 1

In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the
Multiple Choice
08:14
mean time.
mode time.
marginal time.
 In the probabilistic approach to project network analysis, the time estimate