Question: In the project described below, consider only the path ABGH. Compute the expected task time and variance. a . What is the expected path time

In the project described below, consider only the path ABGH.
Compute the expected task time and variance.
a. What is the expected path time for ABGH?
b. What is the path standard deviation for ABGH ?
c. What is the probability that this path will be completed by day 22?
d. For what due date would the probability of completion be 95%?(leave as a non whole number)