Question: In the project described below, consider only the path CEF. Compute the expected task time and variance. optimistic most likely pessimistic expected s 2 Task

In the project described below, consider only the path CEF. Compute the expected task time and variance. optimistic most likely pessimistic expected s2 Task time time time time (variance) A 234 B 468 C 51219 D 4612 E 121522 F 6921 G 126 H 3815 a. What is the expected path time for CEF? b. What is the path standard deviation for CEF? c. What is the probability that this path will be completed by day 42? d. For what due date would the probability of completion be 95%?(leave as a non whole number)