Question: Given a simple project illustrated in the following table Activity Immediate Predecessors Time ( weeks ) 1 - 2 2 1 2 3 2 2

Given a simple project illustrated in the following table
Activity Immediate Predecessors Time (weeks)
1-2
212
322
425
53,43
Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 5 weeks. Given the actual project progress, what is the expected project completion time?
Group of answer choices
13
11
12
10