Question: In this project, how many weeks does the project completion will be delayed if Activity G is delayed by 1 week? Activity Immediate Predecessor(s) START

In this project, how many weeks does the project
In this project, how many weeks does the project completion will be delayed if Activity G is delayed by 1 week? Activity Immediate Predecessor(s) START B D E F G FINISH Activity Time (weeks) 0 5 2 3 4 6 START START B AB DE CE F G 10 4 0