Question: Question 1 In this project, how many weeks does the project completion will be delayed if Activity F is delayed by 2 weeks? Question 2
Question 1
In this project, how many weeks does the project completion will be delayed if Activity F is delayed by 2 weeks?
Question 2
In this project, how many weeks does the project completion will be delayed if Activity G is delayed by 1 week?
Activity Activity Time (weeks) Immediate Predecessor(s) START A B AWN 5 2 3 4 6 10 4 0 START START B A AB DE C, E F G E F G FINISHStep by Step Solution