Question: In your project 60-week project, the earned value analysis shows the following: The project was scheduled to be 35 percent complete at this time. You

In your project 60-week project, the earned value analysis shows the following: The project was scheduled to be 35 percent complete at this time. You have completed 10 of the 19 deliverables (all of equal value). You have spent $15,000 of your total original budget of $120,000. The first deliverable took twice as much as was planned and budgeted. Calculate the following: Budget at completion Actual cost Planned value Earned value Cost variance Cost performance index Schedule variance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!