Question: In your project 64-week project, the earned value analysis shows the following: The project was scheduled to be 30 percent complete at this time. You
In your project 64-week project, the earned value analysis shows the following: The project was scheduled to be 30 percent complete at this time. You have completed 19 of the 20 deliverables (all of e