Question: In your project 64-week project, the earned value analysis shows the following: The project was scheduled to be 30 percent complete at this time. You

 In your project 64-week project, the earned value analysis shows the

In your project 64-week project, the earned value analysis shows the following: The project was scheduled to be 30 percent complete at this time. You have completed 19 of the 20 deliverables (all of equal value). You have spent $40,000 of your total original budget of $200,000. The first deliverable took twice as long and cost twice as much as was planned and budgeted. Calculate the following: - Budget at completion - Actual cost - Planned value - Earned value - Cost variance - Cost performance index - Schedule variance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!