Question: Incorrect Question 5 0 1 pts In a project, Task 9 is showing 5 FS - 3 days under the Predecessors column. This means

Incorrect
Question 5
01 pts
In a project, Task 9 is showing "5FS -3days" under the Predecessors column. This means that:
Task 9 is the predecessor of Task 5, with a lag of 3 days
Task 5 is the predecessor of Task 9, with a lag of 3 days
Task 5 is the predecessor of Task 9, with a lead of 3 days
Tasks 5 and 9 should start at the same time
For more information about task dependencies, please review Module 5 Section A. Dependencies.