Question: Incorrect Question 5 0 1 pts In a project, Task 9 is showing 5 FS - 3 days under the Predecessors column. This means
Incorrect
Question
pts
In a project, Task is showing FS days" under the Predecessors column. This means that:
Task is the predecessor of Task with a lag of days
Task is the predecessor of Task with a lag of days
Task is the predecessor of Task with a lead of days
Tasks and should start at the same time
For more information about task dependencies, please review Module Section A Dependencies.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
