Question: Question 1 1 In a project, Task 9 is showing 5 FS - 3 days under the Predecessors column. This means that: Task 5

Question 1
1
In a project, Task 9 is showing "5FS-3days" under the Predecessors column. This means that:
Task 5 is the predecessor of Task 9, with a lag of 3 days
Task 9 is the predecessor of Task 5, with a lag of 3 days
Task 5 is the predecessor of Task 9, with a lead of 3 days
Tasks 5 and 9 should start at the same time