Question: In a project, Task 9 is showing 5FS - 3days under the Predecessors column. This means that: Group of answer choices Task 9 is the
In a project, Task 9 is showing "5FS - 3days" under the Predecessors column. This means that: Group of answer choices Task 9 is the predecessor of Task 5, with a lag of 3 days Task 5 is the predecessor of Task 9, with a lead of 3 days Tasks 5 and 9 should start at the same time Task 5 is the predecessor of Task 9, with a lag of 3 days