Question: Indicate the activities that are in the critical path Activity Name Preceding Event(s) Expected Duration A - 4 B A 5 C A 6 D

Indicate the activities that are in the critical path

Activity Name

Preceding Event(s)

Expected Duration

A

-

4

B

A

5

C

A

6

D

A

7

E

A,D

6

F

C,E

5

G

D,E

4

H

E

3

I

F,G

4

J

H,I

5