Question: Industrial Building Inc. has two project team installing virtually identical, 4 - story commercial buildings for a customer in two separate cities.Both projects have a
B: A: Cost Day B: Cost 1 2 3 4 5 6 Team Team A: Earned Earned Value Value 90 90 92 88 94 95 98 101 104 89 112 105 95 98 101 106 116 126 95 94 102 109 99 118 No projects in terms of general progress and according to critical