6. Industrial Building, Inc., has two project teams installing virtually identical, four-story commercial buildings for a customer in two separate cities. Both projects have a planned daily cost of 100 and a planned daily earned value of 100 The first 6 days for each team have progressed as follows: Team A: Team B: A: B: Day Earned Value Earned Value Cost Cost 95 95 98 94 0 102 106 109 116 99 126 118 90 92 94 98 104 112 90 95 101 89 105 3 6 Compare the two projects in terms of general progress and according to critical ratios