Question: Industries is installing a new computer system. The activities, the activity times, and the project network die table [ [ Activity , Time ]

Industries is installing a new computer system. The activities, the activity times, and the project network die
\table[[Activity,Time],[A,3],[B,6],[C,2],[D,5],[E,4],[F,3],[G,9],[H,3]]
The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. Afte necessary. The following information is relevant.
\table[[,Time (weeks),Cost ($)],[Activity,Normal,Crash,Normal,Crash],[A,3,1,900,1,700],[B,6,3,2,000,4,100],[C,2,1,500,1,000]]