Question: INFORMATION FOR PROJECT DELTA Activity Description Predecessors Estimated Duration A Contract signing None 5 B Questionnaire design A 5 C Target market ID A 6
INFORMATION FOR PROJECT DELTA
Activity Description Predecessors Estimated Duration
A Contract signing None 5
B Questionnaire design A 5
C Target market ID A 6
D Survey sample B, C 13
E Develop presentation B 6
F Analyze results D 4
G Demographic analysis C 9
H Presentation to client E, F, G 2
- Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
- Identify all paths through the network. Which is the critical path? What is the slack for each path?
- Which activities have slack time?
- Identify all burst activities and merge activities.