Question: b) Calculate the Critical path using CPM tool for the following set of activities along with the Forward Pass? (5 marks) Activity Description Predecessors Estimated

b) Calculate the Critical path using CPM tool for the following set of activities along with the Forward Pass? (5 marks) Activity Description Predecessors Estimated Duration A Contract Signing None 5 B Questionnaire Design A 5 C Target Market ID A 6 D Survey Sample B , C 13 E Develop Presentation B 6 F Analyze Results D 4 G Demographic Analysis C 9 H Presentation to Client E, F , G 2