Question: Information Systems Complete the Activity Table presented in the Case Description by identifying the task precedents in the appropriate column: Generally, Jian has organised the
Information Systems
Complete the Activity Table presented in the Case Description by identifying the task precedents in the appropriate column:
Generally, Jian has organised the tasks in Phase 1 (Analysis & software configuration) and Phase 2 (Testing) in the Activity Table to be completed in sequential order (from 1.1 2.6), but there are exceptions. These are outlined as follows.
- Both tasks 1.2 and 1.3 involve interviewing different user groups, and so can be conducted at the same time.
- The data models and process models require a complete set of user requirements from both user groups.
- Software testing, starting with integration testing (2.3) cannot begin until the software has been fully configured.
- However, the testing plan can be developed (2.1) immediately after the data & process models have been completed (1.4).
- The testing environment can be set up (2.2) after the test plan is complete but configuring the software (1.6) cannot be done until the testing environment is ready.
- User testing of the administration functionality (2.4) can be done independently of the user testing of the principals office functionality (2.5).
- Acceptance testing (2.6) is done only when all user testing has finished.
Segment of the Draft Work Breakdown Structure for the SMS-A Project
| Task Description | Estimated Duration | Predecessor | Who |
|
| (days) |
|
|
|
|
| |
| 1.1 Organise user interviews | 1 |
| Jian |
| 1.2 Gather user requirements (Administration) | 5 |
| Mohammed, Jack |
| 1.3 Gather user requirements (Principal) | 2 |
| Gwen, Aroha |
| 1.4 Create data and process models from reqs. | 5 |
| Mohammed, Gwen |
| 1.5 Perform gap analysis | 6 |
| Mohammed, Jian |
| 1.6 Configure vendor software to meet reqs. | 8 |
| Mohammed, Jian, Gwen |
|
|
|
|
|
|
|
|
|
| 2.1 Create testing plan | 2 |
| Jian |
| 2.2 Create testing environment | 3 |
| Mohammed, Gwen |
| 2.3 Perform integration testing | 6 |
| Mohammed, Gwen |
| 2.4 Perform user testing (Administration) | 8 |
| Mohammed, Jack |
| 2.5 Perform user testing (Principal) | 4 |
| Gwen, Aroha |
| 2.6 Perform acceptance testing | 6 |
| Aroha, Jack |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts