Question: INFORMATION: The following table shows data on the average number of customers processed by the service units of three local banks (A, B and C)
INFORMATION:
The following table shows data on the average number of customers processed by the service units of three local banks
(A, B and C) each day. The hourly wage rate is R30, the overhead rate is 1.1 times labour cost, and material costs is R20
per customer.
Service Unit Number of
employees
Customers processed per day
Bank A
Bank B
Bank C
4
5
8
36
40
80
REQUIRED:
3.1 Compute the labour productivity and the multifactor productivity for each unit. Use an eight-hour day for multifactor
productivity (Round off multifactor productivity to three decimal places). (9 marks)
3.2 Suppose a new, more standardized procedure is to be introduced that will enable each employee to process one
additional customer per day. Compute the expected labour and multifactor productivity rate for each bank (Round off
multifactor productivity to three decimal places). (11 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts