Question: Instructions Assignment #4 - Reducing Project Duration Step One: Use the data below, hand draw an AON network diagram and calculate Forward Pass, Backward Pass,

Instructions Assignment #4 - Reducing ProjectInstructions Assignment #4 - Reducing Project

Instructions Assignment #4 - Reducing Project Duration Step One: Use the data below, hand draw an AON network diagram and calculate Forward Pass, Backward Pass, Slack Time and Critical Path. Clearly identify your critical path. Step Two: You have only 16 days to complete this project. What is the least cost solution to achieve completion in 16 days? Redraw a second AON network diagram by hand showing completion of the network in 16 days and calculate Forward Pass, Backward Pass, Slack Time and Critical Path(s). Step Three: What is the least cost increase to achieve the 16 day duration? Hand write your calculations. Show your calculations to arrive at the least cost increase to complete in 16 days. Cite Sources Activity Preceding Duration Max Crash Slope ID Activity in Days Time A None 3 1 $20 B A 5 2 $60 C A 3 1 $40 D A 10 O $0 E B 6 3 $50 F 7 3 $100 G D,E,F 5 1 $70 Step Four: 1. Submit the two hand drawn AON networks diagrams (Steps 1 and 2) along with your hand written calculations your name and signature, 2. Scan them and place them in a Word document, and submit them to the the Submission Folder

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!