Question: Step One: Use the data below, hand draw an AON network diagram and calculate Forward Pass, Backward Pass, Slack Time and Critical Path. Clearly identify
Step One:
Use the data below, hand draw an AON network diagram and calculate Forward Pass, Backward Pass, Slack Time and Critical Path. Clearly identify your critical path.
Step Two:
You have only 16 days to complete this project. What is the least cost solution to achieve completion in 16 days?
Redraw a second AON network diagram by hand showing completion of the network in 16 days and calculate Forward Pass, Backward Pass, Slack Time and Critical Path(s).
Step Three:
What is the least cost increase to achieve the 16 day duration? Hand write your calculations. Show your calculations to arrive at the least cost increase to complete in 16 days.
DATA:
Activity Preceding Duration Max Crash Slope
ID Activity in Days Time .
A None 3 1 $20
B A 5 2 $60
C A 3 1 $40
D A 10 0 $0
E B 6 3 $50
F C 7 3 $100
G D,E,F 5 1 $70
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
