Question: Instructions: Please type your answers in the gray boxes and expand row heights where needed. Activity B 2 Activity E 5 10 7 Figure 1

Instructions: Please type your answers in the

Instructions: Please type your answers in the gray boxes and expand row heights where needed. Activity B 2 Activity E 5 10 7 Figure 1 Activity G Activity A 12 Activity D 4 15 7 12 Activity H 8 5 Activity C Activity F 20 6 1. Calculate the ES, EF, LS, and LF times and total slack for each activity in the figure 1 above. Activity LED LES EFL LS 2. What is the critical path for the project? 3. How long is the project estimated to take