Question: Instructions: Submit your work as a Microsoft Project file (.mpp) only. Assigned Work: A certain project is defined by the data given in the table

Instructions: Submit your work as a Microsoft Project file (.mpp) only. Assigned Work: A certain project is defined by the data given in the table below. The durations are given in weeks, and the project is scheduled to start on Monday, May 10th, 2021. Task Predecessor Duration A 3 B 2 4 D B,C 3 E A 5 F D 3 Workers 5 2 3 2 3 4 Create a project plan for this project in MSP following our usual conventions, and MSP's Project Summary Task feature to compute the overall project duration. Assign the required workers to each project activity, assuming that each activity starts as soon as possible. If there are only 7 workers available for this project, rearrange the timing of select individual project activities within MSP to ensure that the project can be completed as soon as possible without violating the precedence relationships or the resource limit. The project duration may be extended if necessary. Save your project file under the file name 'FW21b' and submit for grading. In grading your work, I will pay attention to your MSP Gantt chart, network diagram, resource sheet, and resource graph. Instructions: Submit your work as a Microsoft Project file (.mpp) only. Assigned Work: A certain project is defined by the data given in the table below. The durations are given in weeks, and the project is scheduled to start on Monday, May 10th, 2021. Task Predecessor Duration A 3 B 2 4 D B,C 3 E A 5 F D 3 Workers 5 2 3 2 3 4 Create a project plan for this project in MSP following our usual conventions, and MSP's Project Summary Task feature to compute the overall project duration. Assign the required workers to each project activity, assuming that each activity starts as soon as possible. If there are only 7 workers available for this project, rearrange the timing of select individual project activities within MSP to ensure that the project can be completed as soon as possible without violating the precedence relationships or the resource limit. The project duration may be extended if necessary. Save your project file under the file name 'FW21b' and submit for grading. In grading your work, I will pay attention to your MSP Gantt chart, network diagram, resource sheet, and resource graph