Question: _____ is a scheduling tool that assigns three time estimates for each activity ( optimistic, most probable, and pessimistic). This technique allows managers to anticipate
_____ is a scheduling tool that assigns three time estimates for each activity ( optimistic, most probable, and pessimistic). This technique allows managers to anticipate delays and potential problems and schedule accordingly.
Group of answer choices
Value-stream mapping
A Gantt chart
Bottleneck elimination
The program and evaluation review technique LEARNING OUTCOME: 6
Prioritization
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
