Question: _____ is a scheduling tool that assigns three time estimates for each activity ( optimistic , most probable , and pessimistic ) . This technique

_____ is a scheduling tool that assigns three time estimates for each activity ( optimistic , most probable , and pessimistic ) . This technique allows managers to anticipate delays and potential problems and schedule accordingly . The program and evaluation review technique A Gantt chart Prioritization Bottleneck elimination Value - stream mapping The program and evaluation review technique