Question: _____ is a scheduling tool that assigns three time estimates for each activity ( optimistic, most probable, and pessimistic). This technique allows managers to anticipate
_____ is a scheduling tool that assigns three time estimates for each activity ( optimistic, most probable, and pessimistic). This technique allows managers to anticipate delays and potential problems and schedule accordingly. Group of answer choices A Gantt chart Prioritization Bottleneck elimination Value-stream mapping The program and evaluation review technique