Question: It has been estimated that the mean time required to complete a project is 2 0 weeks and the variance of project completion time is

It has been estimated that the mean time required to complete a project is 20 weeks and the variance of project completion time is 9 weeks. So there is a 50% chance that the project can be completed in 1)10 weeks 2)19 weeks 3)20 weeks 4)26 weeks