Question: It takes a company twenty weeks with 2 0 0 workers to build an airplane. Material costs are $ 1 5 million and overhead costs

It takes a company twenty weeks with 200 workers to build an airplane. Material costs are $15 million and overhead costs are $1.5 million. Workers cost $35 per hour including benefits and work 40 hours per week. The airplane sells for $50 million. What is the multifactor productivity ratio of the company?
greater than 2.0 but less than or equal to 3.0
greater than 1.0 but less than or equal to 2.0
less than 1.0
greater than 3.0