Question: It was determined on Project Widget that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined.
It was determined on Project Widget that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. a)Calculate the expected time and variance (using the 95percent confidence level) for each activity.
b)Using the expected times, determine the critical path and time for completion.
c)Calculate the probably that the project will finish in 22days.Calculate the probably that the project will finish in 25 days.
d)Based on theinformation given, calculate the probability that the next riskiest path will be completed in 22 days.
e)Your boss wants to know what time it will take to complete with you being 90% sure. What do you tell her?

Answer the following questions. Completing the questions thoroughly will result in full credit, and the grade will not depend on the content. Be specific.
a)What aspect of the class project did you enjoy the most?
b)What was the biggest issue with your project? How could that have been overcome?
c)What was something that you learned from the project that will be useful in future projects?
d)Did having a real customer improve your performanceor improve the class experience? Explain.
e)Do you see yourself doing service in the future? Has the class experience changed that outlook? Explain.

Activity A B Predecessor Opt. (days) Normal (days) Pess. (days) - 1 2 4 A 2 4 B 3 5 6 B 4 6 8 3 4 12 UI- 2 7 B C,D,E F G HI 5 8 5 11 K 5 Table of Standard Normal Probabilities for Negative Z-scores Table of Standard Normal Probabilities for Positive Z-scores 0 000010 020030. 40 050009708 0.9 4. 40.0300300300030000000000000002 -2.00 15 ! ! ! - 1 4 41 2010-0.0000000000005 L.10.303030300:00. 000 3, 50.10.131300013/00000000000000 23 .0l90. 0 0010 0 ,! $0 014010004000+ ? $000.00 00 00 00 2009 2. 0.50. 30 2009-2012.12.20026 00 000001 2020.000. 000 D50 00320.0050 .00+ d +8 240.2.10.0 0 00 05 0.500- 2. 30.100.140.1020.0090. 0 0 0.911.1830. 07.015 -224.330.03.2015 1220099.01 .020 2.. .0170.0! 70.0-77001560150150.2150150.04004 2. 0.220 .222 .21022027122015 ..01520 . 0 0 1. 9 0.02870.0280.02740.02580 2520025600201.0240.2390023 1. 50. 30.03. 000 0000322030.000.00002 -17 .04 40 450.0 0 0 0 02 0 038 00 03 . 5 0.5130 .05 .250 .021500@ 5043: 0.480. 2.045 .0453 50.06 5 0500000055 . 40.0515007930. 000000000001059403. ->00 50 5 [ 01 01: 31: 30:00 , , 100 101 1030 . 10290.1030098 1 .35 .131412202 219 . 1091 ]. 0.55061530048 20 , 14 013 30.L-0405152136 1 9151 0.21 10.27] 2 0 09 949 --- ,139045 ---33350- 2011-6 -31- 01- 28 04030030 22 024 3003000013006 20432310026 4 - 03-3 0 1 - 1,0303, 1. 3 4.35210.383 . 3303070366903632 .330.3350 .3.2003433 20! - - / 331 - 0 - 0.5 , 030-30 0.43 .4- 0 - 0- 90 . 5 0 2 529 0 - 0.000.01 0.020.030.040 050 0097 98 99 000.000.50400 50500000 30805190338 5390 3 -03 Ll 20 230 23: 20 23 24 23 22 .20-0-30514 L2 .81 30.5210. 65025505 .t 5 L155505050 01 53 205450965D9D2302_ 030- 30---00- 1717507520 2020. . . . 2 L 3399 10.51.55505212052 50 20 2590310. 50 50 535 L15-5030 50 25 0 21 1 0.5543.3550 SEED 550530490.00. 50.51005330 L12 . 49.5 399.32 2033 2037 015 1 031323049090313973252917 1.+1.12.327222026 202 .295220015 1 09 32335093533952090 35.41 94 941 L 15.52. 40 40 40 -950900120530935 035535509592030 50 [ ..$ 0.34 .359999% 94 % 9 4 %9 - ? . . L] 17,37099705095551975? L200. 320. 3307933 150 S020931 53053053053 54 55 50 5 0.3-0.40 502. 220 .40 230.00 22 75 . 50 1 L 2015 020 2022 202703392 30 130.00 - 03 35.5 52 055239509637_0 52 53 5 27 | 0.9630.50.3520.50.39...% 252094 |174017596/ 0 / 0 038 [ 1.33L2.12099090 9 031896093 0051033709730 31 32:05 3535330 50 310.0.108009992020903203 00 30.0. 30 2009