Question: Following are the three time estimates for a task in a project: Optimistic completion time = 4 weeks Most likely completion time = 8 weeks

Following are the three time estimates for a task
Following are the three time estimates for a task in a project: Optimistic completion time = 4 weeks Most likely completion time = 8 weeks Pessimistic completion time = 12 weeks Compute the task variance. esc F1 F2 13 OA) 2.15 weeks 1 2 3 a 3 e B) 1.58 weeks S d OC) 1.23 weeks Z D) 1.78 weeks