Question: Item: Gadgets Current On-Hand Quantity = 140 units Lead Time: 1 week Safety Stock Required: 0 Lot Size Rule: Periodic OQ (POQ) = 3 weeks
| Item: Gadgets Current On-Hand Quantity = 140 units Lead Time: 1 week Safety Stock Required: 0 Lot Size Rule: Periodic OQ (POQ) = 3 weeks Scheduled receipts: 40 in Week 1 | ||||||||||
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | |
| Gross Requirements | 180 |
| 40 | 80 |
| 120 |
| 120 |
| |
| Scheduled Receipts | 40 |
|
|
|
|
|
|
|
| |
| Projected On Hand | 140 |
|
|
|
|
|
|
|
|
|
| Planned Receipts |
|
|
|
|
|
|
|
|
| |
| Planned Order Releases |
|
|
|
|
|
|
|
|
| |
Complete the MRP record based on the information at the top of the table (some which is already filled in), and answer the following questions:
(i) What is the Planned Order Release for the Week 2 ?
(ii) What is the Projected On Hand for the Week 7 ?
Select one:
(i) Planned Order Release for the Week 2: 0 (ii) Projected On Hand for the Week 7: 0
(i) Planned Order Release for the Week 2: 120 (ii) Projected On Hand for the Week 7: 120
(i) Planned Order Release for the Week 2: 0 (ii) Projected On Hand for the Week 7: 240
(i) Planned Order Release for the Week 2: 120 (ii) Projected On Hand for the Week 7: 0
(i) Planned Order Release for the Week 2: 40 (ii) Projected On Hand for the Week 7: 0
Clear my choice
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts