Question: Izzi used a project management software package and has determined the following results for a given project: Expected completion time of the project = 22

Izzi used a project management software package

Izzi used a project management software package and has determined the following results for a given project: Expected completion time of the project = 22 days Variance of project = 2.77 days What time would give Izzi a 95% chance of completing the project? 24.7 days O 4.55 days 0 26.6 days O 2.73 days